شراء اسهم

معالم\milestones



Milestone

Area of Investment/project

Required  financing

2016

تشرين الثاني

Technical Specification NLAP 1.5 MW incineration plant

Basic Development



كانون  الاول

Technical Specification NLAP Facility 2017-2018, Technical Specification Instruments, Part 1 (Steam Control Valve)

Basic Development


2017

كانون الثاني

ٍSteam Control Valve Testrig finished, Waste inlet control finished

Basic Development



شباط

TEMO-IPP Demonstration plant at Qalamoun site in operation

Marketing

25k$


آدار

Ground for production plant ready

Infrastructure

20k$


نيسان

NLAP production plant at Ras Nhache site installed (Hangar)

Infrastucture

30k$


أيار

Detailed Specification&Design according to customers wish finished

1.5 MW plant project



حزيران

Start of manufactoring &installation

1.5 MW plant project



تموز

Manufactoring of Condensor finished

1.5 MW plant project



آب

Manufactoring of Incinerator & Vaporizer finished

1.5 MW plant project



أيلول

Manufactoring of Turbine finished

1.5 MW plant project



تشرين الاول

all mechanical devices installed, piping finished

1.5 MW plant project



تشرين الثاني

Process control system installed and tested

1.5 MW plant project



كانون الاول

wohle plant integration tested

1.5 MW plant project


2018

كانون الثاني

Delivery of plant

1.5 MW plant project



شباط





آدار





نيسان